Warbud's first thermomodernisation contract in the PPP (PFI) formula

On March 1, 2017, Warbud signed a contract for thermomodernisation of 5 school buildings in the commune of Wiązowna in Warsaw east suburbs. It is another Warbud's contract to be implemented as a Public-Private Partnership.

Warbud was represented by Mr Jerzy Werle, Chairman and Mr Mirosław Józefczuk, Board Member. The Client was represented by Mr Janusz Budny, Commune Head. Warbud will carry out the building works in a joint-venture with Siemens.

Construction work will be completed within 19 months. After their completion, Siemens will be responsible for 15 years for technical maintenance of the facilities and for energy management.

The project in Wiązowna is the so-called 'hybrid' PFI project in which three sources of finance are to be used: EU funding, public funds and the private partner's capital.

At present Warbud building the seat of the District Court in Nowy Sącz - the first project in Poland implemented as a Public-Private Partnership (PFI) in which a State Treasury unit is acting as the Public Partner. The contract covers designing, financing, construction and then overall management of the facility for the next 20 years.

Architectural presentation of the Primary School in Glinianka

Architectural presentation of the Middle School Complex in Zakręt

 

This website uses cookies to facilitate your use of its resources. You can change your browser settings regarding the use of cookies. By using this website you agree to accept cookie files. Using our website without changing your browser settings means that cookies will be stored on your device. Detailed information on the use and change of cookie settings can be found in the Privacy policy tab.
Do not show this notification again