Consturcion phases:
1) Phase 1
Reconstruction of the right bank flood protection dyke at the section Lisewo-Palczewo at km 66+000 - 73+000;
length: 2 km, km 66+00 - 68+00
2) Phase 2
Reconstruction of the right bank flood protection dyke at the section Lisewo-Palczewo at km 66+000 - 73+000;
length: 5 km, km 68+00 - 73+00
3) Phase 3
Reconstruction of the right bank flood protection dyke at the section Palczewo - Czerwone Budy at km 73+000 – 86+600;
length: 5 km; km 73+000 - 86+600
Reconstruction of the right bank flood protection dyke at the section Czerwone Budy - Drewnica at km 87+350 - 89+500
length: 2.15 km; km 87+350 - 89+500
4) Phase 4:
Reconstruction of the right bank flood protection dyke at the section Palczewo - Czerwone Budy at km 73+000 – 86+600;
length: 5 km; km 78+000 - 83+000
5) Phase 5:
Reconstruction of the right bank flood protection dyke at the section Palczewo - Czerwone Budy at km 73+000 – 86+600;
length: 3.6 km; km 83+000 - 86+600