Warbud has signed a contract for the construction of a water sports and recreation complex in Koszalin. The contract covers making changes to the design documentation and the completion of Aquapark construction. The Employer is Zarząd Obiektów Sportowych Sp. z o.o. (Sports Facilities Authority Ltd.) in Koszalin.
The contract signing ceremony was held on 2 October 2013 in the headquarters of ZOS in Koszalin. Our firm was represented by Mr Wojciech Gerber, Board Member and Director of Region Centre and by Mr Krzysztof Trzaska, Director of the North Branch.
The scope of the works under the contract covers the "turnkey completion with first equipment" of the development project, in particular:
Plot area: approx. 77 000 m2
Gross cubage: approx. 100 000 m3
Aquapark footprint: 5 389 m2
Footprint of the exterior sauna: 34.7 m 2
Total area: 14 560 m2
Height of building: 16.62 m
Length of building: 120.86 m
Number of floors: 1 underground floor, 4 floors above ground
Project due dates: 21 months following contract conclusion