Warbud has signed a contract for the construction of diaphragm walls of ventilation chambers V14 and V15 for 2nd metro line in Warsaw being built between Daszyńskiego Roundabout and Dworzec Wileński Railway Station in Warsaw.

The Employer is a joint venture of ASTALDI S.p.A., GÜLERMAK A.S. and PBDiM Sp. z o.o.
The contract was signed on 11 May 2012.

Chamber V14

diaphragm walls: 126 m 
wall thickness: 0.60 / 0.80 m

Chamber V15

diaphragm walls: 166 m
wall thickness: 1.00 m

Project dates: May 2012 - September 2012

This website uses cookies to facilitate your use of its resources. You can change your browser settings regarding the use of cookies. By using this website you agree to accept cookie files. Using our website without changing your browser settings means that cookies will be stored on your device. Detailed information on the use and change of cookie settings can be found in the Privacy policy tab.