Warbud in consortium with Eurovia Polska (leader) will build section A of A2 Motorway from Stryków to Konotopa. The contract named “Continuation of designing and execution of building works on the A2 motorway from Stryków to Konotopa along the section from km 365+261.42 (from “Stryków I” interchange without interchange) to km 394+500" was concluded on July 28, 2011.
Warbud will perform the following works:
- completion of building works on 39 civil structures (5 motorway viaducts, 16 road viaducts, 7 motorway bridges, 1 footbridge and 10 wildlife crossings);
- concrete works, waterproofing, corrosion protection and installation of traffic safety systems and carrying out loading tests for the structures.
Scheduled date of completion: October 2012 with ensuring passability for vehicles before UEFA EURO 2012.
The Employer is the General Directorate of National Roads and Motorways.