Warbud has signed a contract with the Inflancka Gynaecology and Obstetrics Hospital for the completion of modernization of Building A of the hospital located at ul. Inflancka 6 in Warsaw.
The works will have a high degree of complexity due to the fact that the hospital will operate without any closures.
The contract covers works such as:
- civil works (fit-out works and equipment installation)
- forced ventilation system, plumbing systems,
- electrical and telecommunications systems,
- medical gases, central heating and process heat installations,
- steam and condensate installations.
as well as delivery and installation of specialist medical equipment.
The execution the contract by Warbud will be a completion of the works of a previous contractor whose contract was terminated by the Hospital. There will be the following units in the modernized hospital: Neonatal Intensive Care Unit, Histopathology Laboratory, a Day Stay Unit, 2 obstetrics units, 2 gynaecology units.
The contract was signed on 26 October 2011.
Duration of contract: November 2011 - July 2012