On April 12, 2018, Warbud signed a contract with Immobel Poland for the first stage of construction works related to the Central Point development project.
The 21-storey building located directly above Warsaw's only intersection of two metro lines (intersection of Świętokrzyska and Marszałkowska streets) will be built on diaphragm walls and barrettes constituting a deep foundation system. Warbud will be responsible for the construction of the diaphragm walls reaching the depth of nearly 39 metres.
Scope of works: diaphragm walls with an area of 3484 m2 and thickness of 80 and 120 cm, 1465 m2 of barrettes
Scheduled project execution dates: April - August 2018